Principalele obiective pentru care s-au proiectat generatoare sunt: |
| |
Beneficiari interni:
Portile de Fier I vertical; 190MVA; 15,75KV; 71,5 rpm;
Portile de Fier II orizontal, 27,5MVA; 6,3KV; 62,5 rpm;
Raul Mare Retezat vertical 186MVA; 15,7KV; 500 rpm;
Lotru-Lotru vertical 185MVA; 15,75 KV; 375 rpm;
Galceag vertical 83MVA; 15,75KV; 600 rpm;
Remeti 60,5MVA; 54,4MVA; 10,5KV; 428 rpm;
Tismana-Aval vertical 2,41MVA; 6,3KV; 214,3 rpm;
-
Ramnicu Valcea vertical 26MVA; 10,5KV; 100 rpm; etc. |
|
Beneficiari externi:
Gezende-Turcia vertical 62,5MVA; 13,8KV; 333,3 rpm;
Kilickaya-Turcia vertical 67MVA; 15,8KV; 214,3 rpm;
Kapulukaya-Turcia vertical 22MVA; 13,8KV; 166,7 rpm;
Dicle-Turcia vertical 65MVA; 10,6KV;200 rpm;
Suat Ugurlu-Turcia vertical 25,5MVA; 11,5KV; 200 rpm;
-
Orta Sakaria-Turcia vertical 14,5MVA; 13,8KV; 150 rpm; etc. |
| |
Obiective pentru care s-au executat motoare electrice:
Butimanu-Dresser Rand, motor sincron 5,1MW; 4,15MW
Combinatul Siderurgic Ispat Galati, motor curent continuu, 2,5MW; 1,1MW, 0,9MW
Siderurgica Hunedoara, motor sincron 3,5MW
I.E. Rovinari, motor asincron, 3,2MW, 7,2MW, 3,1MW, 1,2MW
-
I.E. Turceni, motor asincron, 3,2MW, 7,2MW, 3,1MW, 1,2MW |
|
Obiective pentru care s-au proiectat sisteme de automatizare SCADA:
- CHE Poiana Teiului 2x7MVA
- CHE Subcetate 2x6,98MVA
- HA2 Slatina 13,8MVA
- CINE H.E.P.P. Turcia 2x25MW

| |